Example Asbestos Removal Projects in Marysville

These examples show what one asbestos job looks like, from the house and the test results to the removal method, the days on site and a ballpark cost.

Four lab tests before a split-level remodel

Example project

Split-level entry with carpeted stairs going up and down, small square sample patches on the textured ceiling and a wall, and sealed sample bags on the landing
Home
1970s split-level house in Marysville, lived in by its owners
Original request
Remodel the kitchen and family room, doing some of the work themselves
Testing
Four samples, two from the textured ceiling and two from the walls by the stairs
Found
Asbestos in the ceiling texture
Clear
No asbestos in the wall finish or the joint compound under it
Timeline
A short visit, with results the next day
Estimated testing cost
$480

Scope of work

A visit to take four samples from the materials the remodel will touch, lab fees and a short written report. The ceiling removal is a separate job and price.

Project overview

In this example, the owners of a 1970s split-level in Marysville plan to remodel the kitchen and family room and do the demolition themselves. Owners renovating the house they live in may test it themselves, but they would rather have four samples taken by an inspector before deciding what to do.

The ceiling texture is positive; the walls are clear. The owners hire out the ceilings and open the walls themselves.

The goal

The owners want a clear split between what needs asbestos removal and what they can take out themselves.

Process

  1. Visit Four materials sampled while damp and sealed in labeled bags.
  2. Next day Lab results and a short report.
  3. Then The ceilings are priced for removal; the wall work goes ahead.

Planning right

  • The owner-occupant option covers a remodel of the house you live in. A rental or a teardown needs an accredited inspector.
  • Test before anyone opens a ceiling or pulls up a floor, including you.
  • We give the report to every contractor on the remodel.
  • Cleared materials can be handled the usual way. Keep the report on site.

Get a free quoteMore about testing and remodel abatement

Popcorn ceilings throughout a house before the buyers move in

Example project

Empty living room with a textured ceiling, a wide slider window onto a wet lawn and firs, and plastic over the walls, the floor and a long hall
Home
1970s single-story rambler in Marysville with a wide slider window in the living room, just bought
Original request
Smooth ceilings in every room before moving in
Testing
Texture sampled in four rooms; every sample positive
Area
About 1,600 sq ft of ceiling
Work
Room by room inside plastic, with a notice to the clean air agency first
Timeline
About a week of work between closing and the move
Cost
$13,500

Scope of work

Lab tests of the texture, a notice to the clean air agency, rooms sealed with plastic and a filtered air unit, the texture misted and scraped off, sealed bags hauled to an approved site outside the county, and a final clean of each room. New texture or a skim coat and paint are extra.

Project overview

In this example, buyers close on a 1970s rambler in Marysville and want smooth ceilings everywhere before they move in. An empty house is the easiest time to do it, and the texture tests positive in every room sampled.

A new owner may remove asbestos before moving in, but these buyers hire the work out. The notice goes in first, the house is done room by room in about a week, and the bags travel to an approved site, since none in Snohomish County takes asbestos waste.

The goal

The buyers want clean, bare ceilings in every room before the furniture arrives.

Process

  1. Before closing Samples taken during the inspection period, with the seller agreeing.
  2. Closing week Notice filed; crew and haul booked.
  3. Days one to five Each room gets plastic and filtered air, then the texture is wetted, scraped off and bagged.
  4. Last days Final clean, plastic down, and the painter starts on bare ceilings.

Planning right

  • We take the samples during the inspection period, so the work can start right after closing.
  • An empty house costs less to work in than a furnished one.
  • Smoke alarms and light fixtures come down first and go back up after the paint.
  • File the lab report and waste records with your closing papers.

Get a free quoteMore about popcorn ceiling removal

An older tile layer found under the entry and half-bath vinyl

Example project

Entry hall with patterned sheet vinyl, plastic taped along the walls, the front door and an open half bath with the same floor
Home
1960s single-story house in Marysville
Original request
One new floor through the entry and half bath, level with the front door threshold
Testing
Separate lab tests of the patterned sheet vinyl and an older 9-inch tile layer found under it
Found
Asbestos in the older tile; none in the sheet vinyl on top
Area
About 80 sq ft
Work
Top vinyl lifted the usual way, then the old tile taken up whole and wet
Timeline
One day of removal
Cost
$2,100

Scope of work

Separate samples of each floor layer, plastic along the walls, the toilet pulled by the plumber, the clear sheet vinyl lifted, the old tile below taken up whole by hand and wet, sealed bags hauled to an approved site, and cleanup. New flooring is extra.

Project overview

In this example, the owners of a 1960s house want one new floor through the entry and the half bath, sitting flush with the front door threshold. A cut at the edge shows an older layer of 9-inch tile under the patterned sheet vinyl.

The sheet vinyl on top tests clear, but the tile underneath is positive. Both layers must come up for the floor to sit level, so the vinyl is lifted first and the tile is taken up whole and wet. Intact tile removed this way needs no clean air agency notice.

The goal

The job ends with a clean, level subfloor through the entry and half bath, and the hidden tile gone.

Process

  1. First visit A small cut at the edge, one sample from each layer.
  2. Before work Plumber pulls the toilet.
  3. Removal day Top vinyl lifted, tiles taken up whole and wet, bags sealed and labeled.
  4. Then The new floor goes down level with the threshold, and the toilet goes back.

Planning right

  • A floor that sits higher than it should often has an older floor under it.
  • Tile taken up whole needs no notice; broken or ground tile is treated more strictly.
  • Small floors still need a full setup, so they cost more per foot.
  • Keep the front door closed and use the back door on the work day.

Get a free quoteMore about floor tile and sheet vinyl removal

Survey of a single-wide before it is replaced

Example project

Single-wide mobile home with light siding, green skirting, wood front steps and tall evergreens behind
Home
1970s single-wide on its own lot in Marysville, with wood front steps and tall evergreens behind
Original request
Haul the old home away and set a new manufactured home
Testing
About 12 samples across the unit, taken by an accredited inspector
Found
Asbestos in the kitchen and bath sheet vinyl
Clear
No asbestos in the ceiling panels, wall panels, roof coating or skirting
Timeline
One visit, a report within a few days, then the 10-day demolition notice
Estimated survey cost
$1,100

Scope of work

A survey of every material in the unit, from the roof coating to the floors, about 12 samples, lab fees and a written report for the removal crew and the demolition notice. Removal and hauling the unit away are priced separately.

Project overview

In this example, the owners of a 1970s single-wide on its own lot plan to replace it with a new manufactured home. Taking a home with more than 120 sq ft of roof off its lot counts as demolition, so the whole unit is surveyed first, and owners cannot do this survey themselves.

Only the kitchen and bath sheet vinyl tests positive. Its friable backing comes out before the move, and the demolition notice starts its 10-day wait.

The goal

The owners need clearance to haul the old home away, and only the vinyl has to come out first.

Process

  1. Visit Samples from the roof coating, ceilings, walls, floors and skirting.
  2. A few days later Lab results and the written report.
  3. Next Vinyl removal scheduled and the demolition notice sent in.
  4. After 10 days The old home is taken away and the new one set.

Planning right

  • We check with the dealer or the hauler on the paperwork they need before the old home moves.
  • Roof coatings and patches can test differently. Each one is sampled.
  • Leave the old home empty of furniture before the survey, so every floor layer can be reached.
  • Keep the report with the permit for the new home.

Get a free quoteMore about mobile home asbestos removal

Cement shingles off a garage before it comes down

Example project

Gray cement shingle siding along a one-story house, with a white double-hung window, hostas and a porch at the corner
Home
Arlington house from the 1950s, one story, gray cement shingles and a front porch
Original request
Take down the old detached garage behind the house, which has the same shingles
Testing
One shingle from the garage, sent to a lab, is asbestos cement
Garage
About 280 sq ft of shingle siding
Work
Shingles kept wet and taken off whole before the garage is torn down
Timeline
Demolition notice and 10-day wait, then one day of removal
Cost
$3,600

Scope of work

A sample of one shingle, notices to the clean air agency for the removal and the demolition, plastic on the ground, the shingles misted, nails pulled and each piece taken off whole and wrapped, the haul to an approved site, and the ground picked clean. The garage demolition is priced separately.

Project overview

In this example, the owners of a 1950s house in Arlington want to take down the old detached garage behind it. The garage has the same gray cement shingles as the house, and a sample tests positive.

Cement siding counts as friable, and the garage has more than 120 sq ft of roof, so notices go in for both the removal and the demolition, with a 10-day wait. The shingles come off whole and wet before the garage comes down. The house keeps its siding.

The goal

The garage should be a bare frame ready to come down, with every shingle off in whole pieces and none left in the yard.

Process

  1. First visit One shingle sampled; the garage walls measured.
  2. Before work Removal and demolition notices filed; the 10-day wait runs.
  3. Removal day Shingles misted, unfastened and taken off whole, wrapped and hauled.
  4. Then The garage is torn down and the ground checked for chips.

Planning right

  • Check whether the parcel is in Arlington or Marysville before applying for the demolition permit.
  • Cement shingles break if they are pried. Broken pieces are handled as friable waste.
  • The survey for a demolition has to be done by an accredited inspector, not the owner.
  • The house keeps its siding. Only the garage shingles are part of this job.

Get a free quoteMore about siding and roofing removal

Wrapped ducts out of a crawl space before a heat pump

Example project

Low space under a house with brick walls and wood posts, where large round ducts hang wrapped in torn, papery insulation
Home
Lake Stevens house from the 1950s, one story, ducts under it in a deep crawl space
Original request
Replace an oil furnace with a heat pump and new ducts
Testing
Paper wrap and joint tape both positive at the lab
Work
Every old duct in the crawl space taken out, about 90 sq ft of wrap
Timeline
Notice to the clean air agency, then two days of removal
Cost
$4,300

Scope of work

Samples of the wrap and tape, a notice to the clean air agency, plastic on the crawl-space floor along the duct runs, the ducts wetted, cut into lengths and bagged, a HEPA vacuum of the area, the haul to an approved site and an air check at the end. The heat pump and the new duct system come from the heating contractor’s quote.

Project overview

In this example, an oil furnace in a 1950s Lake Stevens house is being swapped for a heat pump. Under the floor, the old ducts are covered in white paper insulation, torn and loose in many spots. Lab results show asbestos in the wrap and in the joint tape.

The new system gets new ducts, so all the old ones come out first. That is about 90 sq ft of wrap, well over the 48 sq ft that needs a notice, so it goes in before the work. The ducts are wetted and cut inside the crawl space, and the bags leave the county.

The goal

The crawl space ends up empty and ready for new ducts, with the old wrap gone and the house ready for its heat pump.

Process

  1. First visit Samples of the wrap and tape; the crawl space and its access checked.
  2. Before work Notice filed; heat pump install date set.
  3. Days one and two Ducts wetted, cut and bagged in the crawl space, the area vacuumed.
  4. Last step Air check, then the heating contractor runs the new ducts.

Planning right

  • Keep the crawl-space hatch closed until the work is done. Torn wrap sheds fibers.
  • The old oil tank is a separate job for the heating contractor.
  • Disposal sites for asbestos are outside Snohomish County, so the haul is part of the price.
  • If there is vermiculite in the attic, treat it as asbestos and leave it alone until it is tested.

Get a free quoteMore about duct and attic insulation removal